Regional
Monday, November
1, 2004
WB Funds
Avert Power Rationing in Tanzania
By ABDUEL KENGE
SPECIAL CORRESPONDENT
THE WORLD Bank will disburse
to Tanzania part of the $43.8 million energy sector financing that was
approved in July this year.
This follows crucial talks
between the Bank and the Tanzania government last week on how to avert
an imminent power shortage as water levels at three major hydropower dams
dropped sharply.
The meeting, in Dar es Salaam,
between the Bank, Ministry of Energy experts and officials of the Tanzania
Electric Supply Company (Tanesco), also focused on the implementation of
the Emergency Power Project (EPP).
Sources told The EastAfrican
that the funds would be "disbursed immediately" to avoid power rationing
in the period before the onset of the long rains, which start in March
next year.
Tanzania faces a serious
drought in the southern highlands, the catchment areas of the Ruaha river
that supplies water to the three major hydroelectric dams of Mtera, Kihansi
and Kidatu.
The dams’ water levels have
dropped drastically, forcing the government to order the shutdown of the
80MW Kidatu hydroelectric dam with effect from this week.
The three dams produce almost
50 per cent of the 600MW-plus power generated by Tanesco.
The company is now forced
to supplement power from its own generators and from two independent power
generators – Songas (112MW) and Independent Power Tanzania Ltd (IPTL) 100
MW.
There have been frequent
power outages in Dar es Salaam in the past week. However, the effects of
the interruptions on industrial production have not been established.
The WB funds are said to
be intended to avert power rationing in the period between November to
March 2005 when the long rains will set in, and contain three components:
purchasing of fuel to run the Ubungo turbines; purchasing power from IPTL
which is expensive compared with the hydropower generated by Tanesco or
Songas Ltd and the repair of Tanesco’s emergency system.
In principle, the World Bank
approved the project in July this year but the fund was ready for withdrawals
on September 13, according to a government official.
However, some of the loan
components are in still in the implementation stage, since the the agreement
was signed last week.
The emergency power project
was conceived a few years ago after Tanzania experienced its first major
power shortage, following the drought that affected the country in the
mid-1990s. The drought was blamed on over-dependence on hydropower-generated
electricity.
The Minister for Energy and
Minerals, Daniel Yona, last week told The EastAfrican that despite
the adverse weather, Tanzania "will not face power rationing this year
as measures have been in place since January to ensure there is no power
shedding caused by water shortage at the hydro-dams.
"Tanzania has recently reduced
the dependence on hydro-power by almost 10 per cent, to 60 per cent, after
the launch of gas-to-electricity project by Songas Ltd in September," he
added.
Songas has an installed capacity
to generate 180 MW, which will be tapped into when more generators are
installed.
Tanesco’s hydropower system
depends heavily on the dams, among them Nyumba ya Mungu and Hale in northern
Tanzania. The remaining 40 per cent is generated from natural gas and diesel
turbines.
Mr Yona, however, said, The
water inflow level at Mtera, Kidatu and Kihansi is poor due to unsatisfactory
short rains this season. He said that, apart from drawing electricity from
Songas and IPTL, Geita Gold Mining company and Mtibwa Sugar could also
supply power to the national grid should Tanesco require additional power.
Songas expects to generate
up to 180MW by February next year, when two more turbines will have been
installed.
Comments\Views
about this article |